Scope of Work & Bid Specifications

Contractor Scope of Work & Request for Bids (RFP)

Foreword & Contractor Guidance

This document represents the owner's conceptual understanding, proposed workflow, and general intent for the space. It is not cast in stone. Rather than a rigid construction directive, these descriptions and sequences serve as an operational framework to guide your site inspection and estimating process.

While the owner has conducted thorough due diligence to compile and present accurate, realistic, and up-to-date site information and dimensions, it remains the sole responsibility of the contractor to independently inspect the site, field-verify all measurements, and confirm that all existing structural and mechanical conditions are correct prior to submitting a final proposal.

Contractors are expected and encouraged to apply their professional trade expertise, structural judgment, and value engineering. In your bid submission, please specifically detail and outline how you intend to execute each scope item—including your recommended construction methodologies, sequence of operations, structural specifications, and any suggested alternatives that provide superior longevity, structural integrity, or cost efficiency.

Section 1

Base Scope of Work (Required Bid Items)

Task 1: Demolition, Structural Shoring, Joist Remediation, Bearing Point & Basement Footers

Site Dimensions

311" L × 261" W (~25' 11" × 21' 9"), containing 3 interior walls and an existing staircase.

Joist Specifications

True rough-sawn 8" oak beams running across the room width (261" span). Joists are non-continuous / split into two spans, requiring a central load-bearing beam line.

Sequence of Execution
  1. Basement Inspection & Shoring: Inspect and verify the condition, bearing depth, and structural integrity of existing basement footings/piers designated to receive loads from the new ground-floor posts/beam lines. Install temporary structural shoring in the basement as required prior to any load transfer.
  2. Footer Remediation (If Required): Ensure basement footers are adequate and engineered to properly distribute and support the concentrated point and line loads of the new reconfigured layout above. If existing footers are deficient, deteriorated, or undersized, install required underpinning or newly poured reinforced concrete footers.
  3. Main Level Shoring: Construct temporary load-bearing shoring to support both spans of the heavy oak ceiling joists prior to starting any demolition.
  4. Window Infill: Remove existing stair window unit and frame (finished opening: 80" H × 32" W). Infill with solid load-bearing masonry tied securely into the existing wall (aesthetic match not required; surface to be plastered).
  5. Bearing Support: Construct an engineered structural pocket or ledger plate inside the new masonry to serve as the permanent bearing support for the floor joists.
  6. Downstairs Joist Remediation: Inspect existing 8" oak joists while shored. Perform structural sistering (full-depth members, engineered lumber, or flitch plates with approved bolt patterns) or full-member replacement on excessively damaged joists per engineering specifications.
  7. Wall Demolition: Remove all 3 interior downstairs walls only after temporary shoring and masonry bearing points are fully secured.
  8. Permanent Support Installation: Install engineered structural beams/posts to code to carry the split oak joists and eliminate floor deflection. All loads must transfer directly down to the verified basement footings.
  9. Upstairs Wall Removal & Joist Repair (Room 2): Remove the specified dividing wall upstairs in Room 2, and structurally repair/sister any damaged, cut, or deflected floor joists within Room 2 to restore structural integrity.
Contractor Inquiries to Address in Bid:
  • Flush Ceiling Profile: Provide engineered section details (e.g., steel W-beam or flitch system) capable of sitting flush within the existing 8-inch ceiling depth using flush hangers across the ~26 ft (311") span.
  • Sistering Parameters: Confirm engineering parameters for sistering vs. full replacement for damaged heavy timber members downstairs and floor joists upstairs in Room 2.
  • Basement Footing Capacity: Specify any required footer enlargements, underpinning, or newly poured footings necessary to support the proposed beam and post point loads.

Task 2: Masonry Infill (Downstairs Fireplace Area)

  • Remove existing door, frame, trim, and hardware (finished opening: 82" H × 34" W).
  • Infill opening with solid structural brick/masonry matching existing wall thickness (aesthetic match not required; surface will be plastered over).
  • Tie into existing masonry/framing securely.

Task 3: Masonry Infill (Kitchen Area)

  • Remove existing door, frame, and hardware (finished opening: 85" H × 38" W).
  • Infill opening with solid structural brick/masonry tied securely into existing walls on both sides (aesthetic match not required; surface will be plastered over).
  • Finish flush with existing rough wall plane to receive plaster.

Task 4: Masonry Infill (Stairs to Old Section Entryway)

  • Remove existing door, jamb, casing, and hardware connecting the stairwell to the older section of the building (finished opening: 82" H × 32" W).
  • Infill opening with solid structural masonry tied securely into perimeter brickwork to seal off and structurally separate both building sections (aesthetic match not required; surface will be plastered over).
  • Finish flush with existing wall plane to receive plaster.

Task 5: Building Interconnection Doorways (Hallway Cut-Through & Upstairs Dual Fire Doors)

Part A: Hallway Cut-Through (Old Hallway to New Building)
  • Install temporary structural shoring/supports as required on the dividing wall.
  • Cut and frame a new rough opening between the old hallway and new building.
  • Supply and install an engineered structural lintel/header to carry upper wall and roof loads.
  • Frame rough opening and install pre-hung commercial door unit, jamb, threshold, and hardware.
Part B: Upstairs Dual Fire Door Entryways (Old & New Building Separation / Passage)
  • Reconfigure and structurally frame the two upstairs entryways leading from the common stairwell—one accessing the old portion of the building and the second accessing the new portion.
  • Install two commercial-grade, UL fire-rated door assemblies (slabs and frames) providing compliant fire barrier separation between tenant/building zones.
  • Coordinate frame positions, swing clearances, and hardware so that when both doors are unlocked and opened simultaneously, they establish a direct, complete, and unobstructed passageway between the old and new sections of the building.
  • Equip both assemblies with code-compliant commercial hardware, including fire-rated hinges, positive-latching locksets, door closers, and coordinated hold-open devices (such as magnetic hold-opens released upon alarm, if required by local fire code) to maintain continuous unobstructed circulation when desired.
  • Seal and finish door surrounds with approved fire-rated materials and trim to ensure rated assembly continuity.

Task 6: Window Conversion to Bathroom Entry (Old Building)

  • Remove existing window unit, sill, casing, and framing.
  • Saw-cut masonry/framing below sill down to finished floor level.
  • Verify existing lintel capacity (or install new structural header).
  • Frame rough opening and install pre-hung bathroom door unit, casing, threshold, and moisture-resistant sealing.

Task 7: Reconfigure Passageway (Studio to Retail Front)

  • Existing Opening: 100" H × 30" W finished opening.
  • Target Configuration: Standard 48" × 80" (4'0" × 6'8") commercial hollow metal fire-rated door assembly (45-min or 90-min UL label) prepared to serve as a locking, fire-separated communicating door between tenant spaces.
  • Rough Opening: Approximately 52" W × 82"–84" H.
  • Shore wall, remove existing header, infill upper ~20" with solid masonry (aesthetic match not required; surface to be plastered), widen rough opening to ~52", and install new engineered structural lintel.
  • Hardware Timing Option (Itemize Separately): Specialized commercial fire door hardware (heavy-duty/continuous hinges, hydraulic closer, and communicating lockset) does not necessarily need to be ordered or installed at this stage, subject to pricing. Because the entire premises will initially be occupied by a single user without an independent front retail tenant, there is no immediate code requirement for an active fire barrier or closer. Please separate rough opening/frame preparation labor from the fire hardware supply/installation costs so the owner may defer hardware procurement to a later date if desired.
  • Seal perimeters with fire-rated sealant and finish trim.
Section 2

Optional / Add-Alternate Scope (Quote Separately)

Optional Task A: Install 3 Provided Skylight Units & Roof Flashing

  • Cut and frame three rough openings in roof structure, including double headers, trimmers, and rafter reinforcements.
  • Install three provided skylight units (2 on front, 1 on back in stairwell) with manufacturer-approved flashing kits and ice-and-water barrier tie-ins to guarantee watertight integration.
  • Replace damaged roof decking as required.
  • Correctly step flash between the old and new buildings to ensure proper water shedding and weather sealing.

Optional Task B: Studio Concrete Floor Grinding & Surface Prep

  • Diamond-grind existing concrete slab in studio area to remove high spots, old adhesives, contaminants, and sealers.
  • Profile surface (target CSP 2–3) to meet flatness tolerances for direct glue-down engineered hardwood flooring.
  • Vacuum and thoroughly clean slab dust-free for adhesive application.

Optional Task C: Plumbing System Evaluation, Rough-In & Routing (Old & New Areas)

  • Inspect, evaluate, and test existing water supply and drain, waste, and vent (DWV) piping in the old section to verify condition, serviceability, and ongoing functionality following demolition and shoring work.
  • Collaborate with owner on final routing options through the structural framework of the old section to avoid compromising structural joists and bearing points.
  • Rough-in and route code-compliant water supply lines and DWV plumbing to service the new building area (including bathroom facilities and associated fixtures).
  • Provide tie-ins to building main supply and sewer lines, including required shut-off valves, cleanouts, and proper venting per local plumbing code.
  • Perform standard pressure tests on supply lines and functional flow/drain tests across both zones prior to wall and ceiling closure.

Optional Task D: Complete Drywall / Sheetrock Installation & Electrical Trim-Out

  • Drywall / Sheetrock Hanging & Finishing: Furnish and install drywall across all newly framed, remediated, and modified walls, partitions, and ceiling areas (including moisture-resistant boards in wet areas and fire-rated Type X gypsum where required by code). Tape, bed, and finish joints and fasteners to a Level 4 smooth paint-ready finish.
  • Rough & Finish Electrical: Furnish and install all rough wiring, junction boxes, conduits, and circuits necessary to service the renovated configuration in compliance with current NEC standards.
  • Electrical Fixtures & Trim-Out: Supply and install all specified finish devices including commercial/residential receptacles, switches, dimmers, cover plates, and primary lighting fixtures.
  • Testing & Circuit Labeling: Thoroughly test all circuits, outlets, GFCI/AFCI protection devices, and switches for proper polarity, grounding, and operation. Neatly label all added/modified circuits inside the electrical panel.
Section 3

Contractor Bid Submission Schedule (Example Format)

Note to Bidders: The schedule below is an example format illustrating the line-item breakdown (itemizing labor and materials per scope item) expected in your proposal. Contractors may present their pricing using their standard company bid document, provided it reflects a comparable level of detail.

Item Scope Description Labor ($) Material ($) Total ($)
1.0 Base: Task 1 (Shoring, Joist Remediation, Demo, Flush Beam/Posts, Basement Footers, Upstairs Room 2)
2.0 Base: Task 2 (Fireplace Area Infill – 82" × 34")
3.0 Base: Task 3 (Kitchen Area Infill – 85" × 38")
4.0 Base: Task 4 (Stairs to Old Section Infill – 82" × 32")
5.0 Base: Task 5 (Building Interconnection Doorways)
• Sub-item 5a: Hallway Cut-Through & Commercial Door Install: $________
• Sub-item 5b: Upstairs Dual Fire Door Entryways (Unobstructed Passage): $________
6.0 Base: Task 6 (Bathroom Window Conversion)
7.0 Base: Task 7 (Studio to Retail Passageway – 48" Frame/Opening)
• Sub-item 7a: Structural Opening, Lintel & Frame Prep: $________
• Sub-item 7b: Fire Door Slab & Hardware Package (Optional/Deferrable): $________
Total Base Bid $$$
Opt A Optional: 3 Skylights (Install Provided Units, Decking, Step Flashing)
Opt B Optional: Concrete Floor Grinding & Prep
Opt C Optional: Plumbing Rough-In & Routing Evaluation (Old & New Areas)
Opt D Optional: Complete Sheetrock / Drywall & Electrical Trim-Out
Section 4

Contractor Information & Execution Terms (Example Template)

Note to Bidders: The fields below represent an example checklist of the administrative details, insurance verifications, estimated milestones, and authorization disclosures required to accompany your bid submission.